The Council of The Corporation of the City of Thunder Bay has constructed as Local Improvements, works on the following streets between the points mentioned:

The cost of the works, The Corporation’s portion of the works, the owners’ special rate per metre frontage and the annual rate per metre frontage are set forth in the following schedule:

For construction of Curb and Gutter on Frederica Street West from Neebing Avenue to Dead End (cost payable in 15 annual payments).

STREET

FROM

TO

Cost Of Work

Total Annual Payment

Owner’s Cost Per Metre

Annual Rate Per Metre Frontage

FREDERICA STREET W

NEEBING AVENUE

DEAD END

$149,357.53

$12,967.98

$192.3396778

$16.69990587

 

For construction of Sidewalk on Frederica Street West from Bowman Avenue (Unopened) to Machray Avenue (Unopened) (cost payable in 15 annual payments)

STREET

FROM

TO

Cost Of Work

Total Annual Payment

Owner’s Cost Per Metre

Annual Rate Per Metre Frontage

FREDERICA STREET W

BOWMAN AVENUE

MACHRAY AVENUE

$37,767.78

$3,279.19

$104.2963106

$9.055534407

 

For construction of Sidewalk on Frederica Street West from Neebing Avenue to Bowman Avenue (Unopened) (cost payable in 15 annual payments)

STREET

FROM

TO

Cost Of Work

Total Annual Payment

Owner’s Cost Per Metre

Annual Rate Per Metre Frontage

FREDERICA STREET W

NEEBING AVENUE

BOWMAN AVENUE

$34,017.29

$2,953.55

$104.296327

$9.055535826

 

For construction of Curb and Gutter on Kelly Street from Walsh Street to Empire Avenue (cost payable in 15 annual payments)

STREET

FROM

TO

Cost Of Work

Total Annual Payment

Owner’s Cost Per Metre

Annual Rate Per Metre Frontage

KELLY STREET

WALSH STREET

EMPIRE AVENUE

$107,575.44

$9,340.25

$184.624985

$16.03007713

 

For construction of Curb and Gutter on Mountdale Avenue from Mary Street to North End Limit (cost payable in 15 annual payments)

STREET

FROM

TO

Cost Of Work

Total Annual Payment

Owner’s Cost Per Metre

Annual Rate Per Metre Frontage

MOUNTDALE AVENUE

MARY STREET

NORTH END LIMIT

$74,602.19

$6,477.34

$191.013391

$16.58475093

 

For construction of Curb and Gutter on Tungsten Street from Alloy Drive to Central Avenue (cost payable in 15 annual payments)

STREET

FROM

TO

Cost Of Work

Total Annual Payment

Owner’s Cost Per Metre

Annual Rate Per Metre Frontage

TUNGSTEN STREET

ALLOY DRIVE

CENTRAL AVENUE

$120,883.93

$10,495.76

$226.7948631

$19.69147973

 

For construction of Storm Sewer on Tungsten Street from Cobalt Crescent to Alloy Drive (cost payable in 20 annual payments)

STREET

FROM

TO

Cost Of Work

Total Annual Payment

Owner’s Cost Per Metre

Annual Rate Per Metre Frontage

TUNGSTEN STREET

COBALT CRESCENT

ALLOY DRIVE

$105,285.01

$7,576.53

$210.5489651

$15.15154511

 

A Committee of Revision will be held on the 22nd day of March, 2019 at 1:30 p.m. in the S. H. Blake Memorial Auditorium (City Council Chambers) – 3rd Floor, City Hall, 500 Donald Street East, for the purpose of hearing complaints against the proposed assessments or accuracy of the frontage measurements and other complaints which persons interested may desire to make and which is by law, cognizable by this Court.

 

Any person who owns a lot to be specifically charged may file an objection, setting out the objection and the reasons in support of it, with the Deputy City Clerk no later than seven (7) days before the date of the Committee of Revision.

Dated at the City of Thunder Bay this 7th day of March 2019.

Krista Power, Deputy City Clerk
Office of the City Clerk
500 Donald Street East